The Construction

30th July 2024

100% Complete!

Construction Complete

Early July 2024

99% Complete!

Construction Progress

1st July 2024

98% Complete!

Construction Progress

Late June 2024

97% Complete!

Construction Progress

Late May 2024

95% Completion!

Construction Progress

May 2024

Exterior Update

Construction Progress

Early April 2024

Pre Completion Update!

Construction Progress

Early March 2024

Level 3 Scaffold Removal

Construction Progress

Early Feb 2024

Level 4 & 5 Scaffold Removal

Construction Progress

January 2024

Wall Linings, Render & Rough Ins

Construction Progress

Early December 2023

Render & Rough Ins

Construction Progress

Early November 2023

Internal Construction Update

Construction Progress

Late October 2023

Roof Completion

Construction Progress

End September 2023

Fifth Level & Final Slab Pour

Construction Progress

Early September 2023

Level 4 Slab Pour

Construction Progress

Late August 2023

Level 4 Slab Prep and Basement Nearing Completion

Construction Progress

Early August 2023

Level 3 Slab Pour

Construction Progress

Early August 2023

3rd Floor Formwork

Construction Progress

Late July 2023

Level 2 Progress

Construction Progress

Early July 2023

Level 2 Progress

Construction Progress

Late June 2023

First Floor Slab Poured

Construction Progress

Early June 2023

First Floor Formwork & Scaffolding

Construction Progress

End May 2023

First Floor Formwork & Retaining Walls

Construction Progress

Mid May 2023

Ground Floor – Transfer Slab

Construction Progress

Late March 2023

Ground Floor Formwork

Construction Progress

Early March 2023

B2 Slab Poured

Construction Progress

Mid Feb 2023

Basement B2 Slab Poured & Formwork Commenced

Construction Progress

Late Jan 2023

B2 Footings & Plumbing

Construction Progress

Early Jan 2023

Excavation Complete

Construction Progress

Early December 2022

Excavation 90% Completed & Crane Installed

Construction Progress

Early October 2022

Site Excavation

Construction Progress

Early September 2022

Excavation Commenced

Construction Progress

End August 2022

Demolition Complete – Excavation to Commence

Construction Progress

Mid August 2022

Site Clearing – Houses Gone – Demolition Almost Complete

Construction Progress

Late July 2022

Site Established, Temporary Fence & Safety Signage

Construction Progress